Owner : Seaport Authority
Status : Completed
Description
• Determination of the structural and watertight conditions of the dry-dock
and to ascertain the status of dry-dock systems, a detailed engineering analysis
and a Salvage Plan involving extensive preparatory work both topside and underwater.
• Maintenance for both the hull and the submerged top deck
including under-water welding and full inspection.
• The floating process has been executed by using a sufficient number of high-capacity
electric salvage pumps. Additionally, numerous gauging systems
were established to monitor tank pressures and condition throughout the refloating operation.